NOTES - SPECIAL MEETING REGARDING THE TH#1 FLOOD AUDIT
SEPTEMBER 30th, 2002
NEWFANE TOWN OFFICE

PRESENT:
Fred Costello- FEMA, Floyd Roberts - District #2 Administrator, Paul Gould - District #2 Tech IV, Gary Shelley - Maintenance Program Administrator (VTAOT), Peter Boomage - Southern Vermont Engineering (via telephone), Jesse Anderson, Selectman, James Gray, Road Foreman, and Doris Knechtel, Administrative Assistant

1. CALL TO ORDER
The purpose of the meeting is to go over the open questions on the South Wardsboro Road (TH#1) Flood Audit beginning at 10:00 a.m.
2. SOUTH WARDSBORO ROAD (TH#1) FLOOD AUDIT
The open questions on the South Wardsboro Road (TH#1) flood repair Phase II audit package was discussed. The phases of the project were reviewed. Phase I was damaged blacktop removal and rough grading to facilitate traffic. Phase II was the rebuilding of the road. Phase III was to blacktop to new construction.
F. Costello explained that the largest open question was the lack of documentation of the bid process for phase II. P. Gould was present at the pre-bid site visit on 10/05/00. He explained that all of the phase I bidders were present and reviewed the work scope. Each received a bid package. These included:
Bazin Brothers, Cersosimo Industries, Gurney Brothers, Zaluzney, Fitzpatrick Excavating, Farnsworth Construction and Daniels Construction.
Board of Selectmen's meeting minutes record that the bids were opened on 10/10/2000 due to the lateness of the construction season. Fitzpatrick Construction was the only bidder.
The other open questions concerned the quantities and types of gravel used. There were also questions about the number of culverts and the treatment of the inlets of these culverts (head walls). All of these questions were discussed and sound technical justifications were determined for each. Fred Costello of FEMA agreed to document these justifications in his submittals.
Some of the observations during the meeting:
* D. Knechtel noted that the original estimated quantity of bank run gravel was 7,500 cubic yards.
* P. Gould noted that the thickness of the blacktop changed from about 12" per flood to about 4.5" as-rebuilt.
* Peter Boemig noted that the notations on the SVE drawings of Existing Grade and Final Grade mean Pre-Flood and Post-Repair. These grades were taken from the top of the asphalt.
* The differences between the Existing and Final Grades were characterized by P. Boemig (SVE) as very minor tweaks.
* A review of the drawings showed that the SVE drawings do not show the addition of the so-called lateral culvert. This culvert will need to be shown on the drawings i
n order for the Environmental Review to be completed, which it must be because this is a change in the project. This is according to F. Costello in consultation with other FEMA personnel in the Boston office whom he contacted during the meeting. This was the only culvert not shown on the drawings.

3. ADJOURNMENT
The Special Meeting was adjourned at 12:05 p.m.

Jesse W. Anderson
Road Commissioner and Selectboard Member

NOTES - SPECIAL MEETING - OCTOBER 2nd, 2002
NEWFANE TOWN OFFICE - 1:00 p.m.

PRESENT:
Peter Thomas - FEMA, Peter Boemig - Southern Vermont Engineering, James Gray - Road Foreman and Doris Knechtel - Administrative Assistant.

1. CALL TO ORDER - 1:00 p.m.
The purpose of the meeting was to have P. Thomas of FEMA review the South Wardsboro Road (TH#1) plans prepared by P. Boemig of Southern Vermont Engineering for environmental clearance.
2. SOUTH WARDSBORO ROAD (TH#1) FLOOD REPAIR PLANS
Peter Thomas of FEMA Environmental, reviewed the plans prepared by P. Boemig of SVE as they relate to the drainage. It seems that there were 14 culverts approved on the original PW for the project and a total of 18 were installed. P. Boemig submitted a hydraulic study to Mr. Thomas. D. Knechtel submitted a list of culverts that were installed with their station numbers. Two culverts were swapped at station 31.50 and 33.25 and an additional CPEP culvert of 24" X 124' , which is not on the revised plans, was added to the ditchline. Mr. Thomas reviewed the reasons for the number of culverts installed and the reasons with P. Boemig and J. Gray. The three of them then went to visit the site. When Mr. Thomas returned, he indicated that he approved of the total 18 culverts that had been installed with the explanations given.
3. ADJOURNMENT
The special meeting was adjourned at 2:00 p.m.

Doris A. Knechtel
Administrative Assistant
Newfane Board of Selectmen

Posted: Newfane Town Office, Newfane Store, Williamsville General Store, Williamsville Hall and South Newfane General Store & Deli.
www.newfanevt.com

Back to top


back to homepage



Town Offices:
Route 30, P.O. Box 36, Newfane VT 05345, Tel. (802) 365-7772

Please send all comments, suggestions and questions to info@newfanevt.com